Delivery dates “estimates only” — why we strike it every time

The sentence appears in most supplier templates, usually in the delivery clause and usually in a reasonable tone: “Delivery dates are estimates only and the Supplier shall not be liable for any delay.” It reads like housekeeping. It is the removal of the buyer’s only remedy for late delivery.

A buyer with that clause has no claim when the goods are late, no right to cancel the affected order, and no leverage in the conversation that follows, because the supplier is in compliance. The clause does not need to be replaced with liquidated damages — most buyer playbooks do not ask for them — but it does need to be replaced. The position: delivery dates are binding; if the supplier fails to deliver within a short grace period after the agreed date, the buyer may cancel the affected order without charge and source elsewhere, without prejudice to its other remedies. Ten business days is a common grace period for standard goods; shorter for time-critical ones.

Suppliers accept this far more often than their template suggests, because their own customers’ templates say the same. Where a supplier resists, the fallback is a two-tier clause: a target date that is an estimate and a long-stop date that is binding, with the cancellation right attached to the long-stop. What the desk will not leave in a buyer’s contract is the sentence as written.

General information, not legal advice. This page describes how EU and cross-border commercial contracts commonly work; it is not advice on your situation, and no engagement arises until a service agreement with Icon.Partners is signed. For advice on a specific contract, speak to a lawyer qualified in the relevant jurisdiction.

Next step

Seen something like this on your own paper?

Send it over. Twenty minutes, marked up, explained.

Book a contract call